Updated on :1 Mar 2010 

Mile Stone
Tower 1
Tower 2
Sl. No
Description
Status
Remarks
Sl. No
Description
 Status
Remarks
1
Plumbing floor work (upto 14th floor, 15c & 16c)
Completed
Nil
 
1
Plumbing and concealing (except combined floors)
Completed
Nil
2
Tiling work ( 6A,9A,12c,15c & 16c)
Completed
Nil
 
2
Plumbing floor work (3-11th floor) Completed
Nil
3
Window grill work
Started
Nil
 
3
Window grill work Started  
4
Lobby first coat putty work
Completed
Nil
 
4
Tiling work (3d,4e,,5d,5e,6d,6e,8e & 9d) Completed
Nil
5
Cornice work (Upto 16th floor)
Completed
Nil
 
5
Lobby first coat putty work Completed
Nil
6
First coat emulsion (6A & 9A)
Completed
Nil
 
6
First coat emulsion (3D,5d,6e,9d)
Completed
Nil
7
Fire System work branch line (A, B & C block)
Completed
Nil
 
7
Fire System work branch line ( except combined floor)
Completed
Nil
8
False celing work (6A, 9A ,12a, 12c, 15c,16c )
Completed
Nil
 
8

False ceiling work (3d,4e,5d, 5e,6d,7d,7e, 8e, 8d,9d, 9e )

Completed
Nil
9
 Second coat putty work (5a, 6a, 9A ,12a, 12c,15c & 16c )
Completed
Nil
 
9
Cornice work (Upto 11th floor) & Second coat putty work (3d,4e,5d,6d & 6e)
Completed
Nil
10
Toilet slab work (upto 10th floor)
Completed
Nil
 
10
Tolilet slab work (3-11th floor) Completed
Nil
Work Progress
Tower 1
status status status
Tower 2
status status status